Water Plant Update – 7-18-2025

July 18, 2025

The project at the water plant is nearing completion. The new filter system startup is scheduled to being on July 22nd. The startup will mean filtered water will need to be wasted to the sewer until all filters are fully acclimated and ready to be put into service. The acclimation period could take as little as a week (if using our pilot media – works well) or 3-4 weeks (if the pilot media didn’t help)